Prepare the wooden
or concrete floor area
for the Tuff-Form Wet
Floor Former,
according to the
installation
instructions provided. |
|
Install Tuff-Form Wet
Floor Former,
drainage pipes and
the relevant waste
outlet according to the
installation
instructions provided.
* Use plywood to raise floor
level to the installed height of
the Tuff-Form Wet Floor
former |
|
Fit Mapei Waterproof
tape, Outlet Gasket,
Pipe Gasket and
Internal corners to
the Tuff-Form Wet
Floor Former, wall
and floor edges
according to the
installation
instructions provided. |
|
Apply two coats of
Mapegum WPS to Wet
floor former and floor
area (walls optional)
according to the
application
instructions provided. |
|
Fit the Stainless Steel
cover to waste outlet
according to the
Installation
Instructions provided.
Shower area is now
ready for tiling and
underfloor heating
can be considered.
|